Earthworks in the Far North can fall under three sets of rules. The district plan and the earthworks bylaw belong to Far North District Council, and the regional plan belongs to Northland Regional Council. We work out which ones apply to your site and prepare the applications.
FNDC says that earthworks deeper than 500 mm over an area of more than 50 m², or more than 50 m³ in volume, need some form of permit. The table shows the three approvals and when each applies.
| Approval | Issued by | When you need it |
|---|---|---|
| Land use consent | Far North District Council | The earthworks exceed the district plan's permitted standards for your zone, such as the volume or the height of cut and fill, or they sit in an overlay with tighter rules |
| Earthworks permit | Far North District Council, under the Control of Earthworks Bylaw | The earthworks are over the bylaw trigger but within the district plan standards. No permit is needed when a resource consent already covers the work |
| Regional consent | Northland Regional Council | Large areas of earthworks, or earthworks near streams, wetlands, the coast or on erosion-prone land |
Some Proposed District Plan earthworks rules already have legal effect. They require earthworks to follow Auckland Council's erosion and sediment control guideline, GD05. See FNDC resource consent and NRC resource consent for how each council works.
Most earthworks consents in the Far North come from one of these four jobs.
Cutting a platform and driveway into a sloping site is the most common trigger. The earthworks are usually lodged with the resource consent application for the house.
The cut behind a retaining wall counts as earthworks. Walls over about 1.5 m usually need building consent too, and walls near a boundary can break district plan rules.
Work in or near a stream or wetland falls under regional rules, so it needs an NRC resource consent as well as any district approval.
New accessways, building sites and drainage for a subdivision are assessed with the subdivision consent, so we plan them together.
Council needs to see how much soil moves, where it goes, and how sediment is kept on site.
Earthworks already done without approval can be dealt with through a retrospective resource consent. For fees, see resource consent cost.
From first look to approval
We check your zone, overlays and nearby waterways against the district plans, the bylaw and the regional plan.
We tell you whether you need a permit, a district consent, a regional consent, or nothing at all.
We prepare the plans and assessment with your contractor or engineer and lodge with the right council. Where both councils are involved, the applications go in together.
We review the conditions with you so your contractor knows the sediment controls and any seasonal limits before work starts.
Common questions about earthworks rules in the Far North
FNDC says that earthworks deeper than 500 mm over an area of more than 50 square metres, or more than 50 cubic metres in volume, need some form of permit. Whether that is an earthworks permit or a resource consent depends on the district plan limits for your zone. Regional rules can apply as well, whatever the volume, when the work is near water or on erosion-prone land.
An earthworks permit is issued under FNDC's Control of Earthworks Bylaw. A resource consent is issued under the Resource Management Act when the earthworks exceed the district plan's permitted standards. If a resource consent is required, FNDC does not also require an earthworks permit.
Sometimes. Northland Regional Council's rules cover large areas of earthworks, earthworks near streams, wetlands and the coast, and earthworks on erosion-prone land. A project can need consent from NRC, from FNDC, or from both.
It depends on the volume, the depth of cut and fill, and where the work sits. A flat site in town often stays within the limits. A sloping rural or coastal site often does not, because the cut for a platform and driveway adds up quickly.
NRC advises keeping open earthworks to a minimum from May to September, and some consents ban earthworks in that window. Plan the consent early so the work can be done in the drier months.
You can apply for a retrospective resource consent. Council assesses the work the same way it would have beforehand, and it can require remedial work such as stabilising cut faces or sediment control.
Sources: FNDC, before you apply for a resource consent, FNDC Control of Earthworks Bylaw, Regional Plan for Northland and Resource Management Act 1991. This page is general guidance, so check your own site before you start work.
Free initial chat. We'll tell you which approvals your site needs.
Check My EarthworksFree initial assessment — we'll check your property and give you a clear answer